BUILDING PROJECT UPDATES
Construction Update: Week of 12/01
Last week 12/08 to 12/12:
Forner Electric was onsite making up the light poles in the paved area and
also erected the five light poles in the paved area
• JH Plant Scapes arrived onsite and delived the remaining pallets of SOD to
complete both Large and Small Sports fields
• JH Plant Scapes sprayed hydro mulch to the areas in which called for hydro
mulch seeding around the fields and areas behind the curbs
Looking Ahead: Week of 12/15 to 12/19
What’s Happening On-Site:
Ensure all new SOD is being watered
• Clean up all areas where SOD installers may have left trash or mud
• Begin to move construction material and storage containers to the area in
which construction is still needing to be completed but are on hold by the County
NEW SPACE TO EXPERIENCE SERVICE
We’re excited to share that we’ve created a new family-friendly space in the lobby. It features comfortable seating, a live video feed, and a more sensory-friendly volume. If your little ones get restless during service, you can step out to minimize distractions for those around you while still staying engaged with the service. This space is also available if you simply prefer a quieter, sensory-friendly experience or if it gets too tight in the main sanctuary.
Stay in the Loop!
Join our Building Project Updates mailing list. You’ll receive the latest news, construction progress, parking updates, and important announcements directly to your inbox.